Currently available auctions / offers: 2

Auction Terms 2 December 2022

Auction Terms 16 November 2022

CURRENT INFORMATION

Operational information

Daily storage inventory in Zone MND ESG
From:
To:
Date: Current capacity in TWh Withdrawals (GWh/day) Injections (GWh/day)
20.11.2026 0.698 8.297 0
21.11.2026 0.697 1.120 0
22.11.2026 0.693 4.466 0
23.11.2026 0.688 4.741 0
24.11.2026 0.676 11.941 0
25.11.2026 0.664 11.941 0
26.11.2026 0.652 11.941 0
27.11.2026 0.640 11.941 0
28.11.2026 0.629 11.533 0
29.11.2026 0.617 11.941 0
Shutdowns and maintenance
Date of Limitation Description of Storage Services Limitation – Zone Other Restrictions Additional Information
6.2. – 20.2.2023 100% of withdrawal rates valid at time of limitation, injection rates unaffected   Reactive maintenance at UGS Hähnlein due to technical failure
23.6.2021, 4 hrs 50% of injection rates valid at time of limitation   Maintenance – UGS Haehnlein
1.10.-20.10.2018 10% of withdrawal rate will not/is not available at time of limitation   Workover Stockstadt S1 – UGS Stockstadt
1.9.-20.9.2018 15% of withdrawal rate will not/is not available at time of limitationung nicht verfügbar   Installation of filterseparator UGS Hähnlein
20.11.-24.11.2017 50% of withdrawal and injection rates valid at time of limitation   Installation of turbine (commercial measurement ) UGS Stockstadt
31.8.2016 (7:00-17:00) 50% of withdrawal rates valid at time of limitation   Maintenance at UGS Hähnlein
30.8.2016 (7:00-17:00) 50% of injection rates valid at time of limitation   Maintenance at UGS Hähnlein
4.8.2016 (7:00-17:00) 50% of withdrawal/injection rates valid at time of limitation   Maintenance at UGS Hähnlein
19.7.2016-21.7.2016 50% of withdrawal/injection rates valid at time of limitation  

Maintenance on Main-Neckar pipeline (see OGE web pages)